Progress
282 days from first to latest action, across 3 recorded actions.
Filed
Jan 13
Referred to committee
Jan 13
Heard in committee
Mar 16
Reported from committee
Mar 16
Passed first chamber
Passed second chamber
Sent to governor
Became law
Filled marks are milestones (committee report, floor passage, governor action). Larger marks hold more same-day actions.
Record votes
Each dot is one member, grouped by how they voted.
Reported out of Assembly committee with amendments
General Assembly · Mar 13, 2026Party-line vote
Passed 7–3
7 Yea
3 Nay
0 Absent / not voting
Reported out of Assembly committee with amendments
General Assembly · Oct 22, 2026Party-line vote
Passed 9–4
9 Yea
4 Nay
2 Absent / not voting
Full history
Every action recorded by New Jersey Legislature.
Reported out of Assembly Comm. with Amendments, 2nd Reading Appropriations
Oct 22, 2026 · General Assembly
Reported out of Asm. Comm. with Amendments, and Referred to Assembly Appropriations Committee Appropriations
Mar 16, 2026 · General Assembly
Introduced, Referred to Assembly Telecommunications and Utilities Committee Telecommunications and Utilities
Jan 13, 2026 · General Assembly
Authors
and 3 coauthors or sponsors
- Robert KarabinchakD
- Bailey, David, Jr.–
- Lisa SwainD
Show 3 more
- Sampson, William B., IV cosponsor–
- Chris Tully cosponsorD
- Heather Simmons cosponsorD
In committee
- Telecommunications and Utilities
General Assembly
Referred Jan 13, 2026 · heard Mar 16, 2026 · reported after 62 days
- Appropriations
General Assembly
Referred Mar 16, 2026 · heard Oct 22, 2026 · reported after 220 days